Correction of Name/ Reg/ Subject in 2010 to 2015 marksheets: Notice in English | Notice in Bengali PG ADMISSION 2017-19 Contractual Employment Notification No. 1/2016? UGC 2F Cetificate of WBSU, Barasat UGC 12B Cetificate of WBSU, Barasat Rules for Review of Results - 2017 Rules for Self-inspection of evaluated answer scripts SPIO Notification Regarding Self Evaluation of Scripts Rules for the Post Publication Re-Examination of answer papers for the M.Ed / B.Ed / B.Ed (H.H.) / B.P.Ed / M.P.Ed.

Available infrastructural facility at West Bengal State University

Total Plot Area : 28.88 Acres = 1,16,900.1 Sq.M.
Total Ground Coverage : 10765.00 Sq.M. (including proposed Food Court building with Ground Coverage = 307.50 Sq.M.)
Sl. No. Building Name with brief details Ground coverage Area/ Total floor Area(Sq.M) Status of Building
1 Guest House Building (Ground+ 2 Storied building) 1582.00/4462.00 Completed with electricity, water, sanitation facilities. All Academic and Administrative activities are presently being operated in this building with Laboratories installed for Science Departments.
2 Boys' Hostel Building(Ground + 2 Storied Building) 1500.00/4300.00 Completed with electricity, water, sanitation facilities. 30 inmates are presently using the facility at first floor level of this building.
3 Girls' Hostel Building(Ground + 2 Storied Building) 1500.00/4300.00 Completed with water & sanitation facilities. Only internal electrification works are balance.
4 33 Kv Electrical Sub-Station(Single Storey Building) 655.00/601.25 Completed with all facilities like installation of Transformers, Switchgear, VCB's & internal electrical connectivity works. The Sub-Station was energized 02/01/2014 by M/s West Bengal State Electricity Distribution Company Ltd. Feeding electrical power to all completed buildings including those under construction/partially completed.
5 Composite Main Building (Academic + Administrative +Library/ Laboratory Building.) Originally planned for Ground+7 stories 5220.00/29035.37 Partially completed with electricity, air-conditioning, false ceiling, water, sanitation facilities upto Ground+3rd Floor Roof level.
6 Street Lighting/Area Lighting   Completed